Suncrest 230kV Loop-in Project
Overview
Our commitment to providing clean, safe and reliable energy means making our system more reliable and resilient for the communities we serve.
The Suncrest 230kV Loop-in Project was identified by the state’s electric grid operator, the California Independent System Operator (CAISO), in its 2022 – 2023 Transmission Plan to help ensure grid reliability.
This project would connect an existing transmission line near El Cajon to SDG&E’s Suncrest Substation, located south of I-8 and east of Alpine. This transmission line would be approximately 14 miles in length and would be primarily overhead, with an underground segment tentatively proposed to be placed along La Cresta Road near El Cajon.
Project Benefits
- Upgraded transmission capacity to improve the reliability of the network
- Enhanced reliability by decreasing overload on existing transmission lines
- Increased operational resiliency by upgrading substations for smoother power flow
- Improved reliability of electric system during extreme weather conditions
About the Project
The Suncrest 230kV Loop-in Project is in the eastern part of San Diego County. An existing 230kV transmission line runs from SDG&E’s Sycamore Canyon Substation near Scripps Ranch to SDG&E’s Miguel Substation near Spring Valley. This transmission line will be extended approximately 14 miles to SDG&E’s Suncrest Substation near Alpine. As part of this project, the Suncrest substation will be upgraded to distribute the energy and support with the existing load.
Most of the transmission line will be constructed overhead, with approximately three miles placed underground near El Cajon. In addition to providing enhanced reliability and operational resiliency, the Suncrest 230kV Loop-in Project will also increase SDG&E’s capability to import more renewable energy from Imperial Valley.
What to Expect
During work hours, traffic delays and temporary lane closures can be expected. SDG&E plans to have traffic control measures in place during construction and our crew will strive to minimize any impact to you and your neighbors. Work along the route may occur intermittently and construction activities required in a certain area may not be completed concurrently. There will be multiple construction locations and activities taking place simultaneously with work hours, traffic control measures and noise restrictions for each area established by local jurisdictions.
Project Schedule and Map
Estimated start date: 2027
In-service date: 2032
FAQ
The project is designed to enhance reliability to the region and enhance SDG&E’s capability to import more renewable energy from Imperial Valley. It will extend a double-circuit transmission line from the current transmission line between the Sycamore Canyon Substation, near Scripps Ranch, and the Miguel Substation, near Spring Valley, and extend it west to the Suncrest Substation east of Alpine. This region was identified as at risk of overloads and potential outages due to insufficient transmission capacity.
The existing transmission line between the Sycamore Canyon and Miguel substations runs north to south just east of the City of El Cajon. This line will be connected to the new double circuit transmission line, which will run east toward Alpine. Approximately three miles of the line will be underground along La Cresta Road in a more densely developed area. As the route moves east, it will transition to above ground. Near the Loveland Reservoir, the route roughly follows Japatul Road to the south. The last approximately three miles of the route turn northeast and follow an existing 500 kV transmission line to the Suncrest Substation east of Alpine.
This project was identified by the state grid operator, the California Independent System Operator (CAISO), in its 2022 – 2023 Transmission Plan as necessary to improve grid reliability and address operational constraints in the region. The proposed transmission line would span approximately 14 miles, connecting an existing transmission line near El Cajon to SDG&E’s Suncrest Substation, located south of I-8 and east of Alpine. Most of the transmission line will be overhead, with a potential underground segment along La Cresta Road.
When siting a transmission line, there are a number of factors we consider including cost, environmental impacts, community impacts and engineering constraints. There is also a state policy, called the Garimendi Principles, that encourages siting new transmission facilities in the same corridors as existing rights-of-way, where feasible. In this case, we were able to consolidate transmission lines on the eastern portion of the project in an existing 500 kV corridor. From the existing corridor the route runs west in a manner that avoids adding excessive distance while avoiding scattered residential areas.
As the route gets closer to El Cajon, the area becomes more developed so the line will need to be placed underground to be cost-effective.
This project will require review and approval of the California Public Utilities Commission (CPUC) before it can be constructed. This review will begin with filing an application in late 2025. The CPUC review will include public hearings and opportunities for comment.
If approved by the CPUC, the project would begin construction around 2027 with a completion date expected in 2032.
More Information
If you have questions, please call the Project information Line at 1-844-765-6388.